BESS control logic after MARI: the short answer
On 2 December 2026 the Polish TSO, PSE, operationally joins the European MARI platform. From then on, BESS control logic matters more for results than the battery itself. In practice an EMS needs a single source of truth for state of charge, available power and grid connection limits, a clear ranking of services, and the ability to control equipment from different manufacturers. Market rules will keep changing, so these settings should be changeable through configuration rather than a new software project each time.
The market is growing. According to PSE data reported by Gramwzielone.pl, battery storage in Poland totalled 1.3 GW of power and 3 GWh of capacity as of 1 October 2026. The more assets there are, the more a given site's result depends on how it is operated, not only on the cells. This article is for mid-size companies that own a battery (often together with PV) or are planning one, and want to understand what the change on the balancing market means for control.
What exactly changes on 2 December 2026
In its TSO announcement of 18 November 2026, PSE states that it will operationally connect to MARI on 2 December at 10:00 CET. MARI is the platform for exchanging balancing energy from manual Frequency Restoration Reserves (mFRR). Connecting is mandatory under the EU Electricity Balancing Guideline, Regulation 2017/2195, as PSE notes in its information on MARI. According to e-magazyny.pl, the rules for Poland's participation were approved by the President of the Energy Regulatory Office (URE) in a decision of 18 November.
From the connection date, all Polish mFRRd (standard product) bids are submitted to MARI, but their activation is restricted during a transition period from 2 December 2026 to 2 December 2027. The cross-border limit (the Technical Profile) widens in steps:
PSE says activation is to be decided by the price of mFRR energy, subject to available cross-border capacity. Nobody guarantees specific prices or revenues, and joining the platform does not automatically admit every installation to this activity. For planning, the takeaway is simple: do not build a business case on the border being fully open from day one.
The product split is also worth knowing. In drafts consulted this autumn, PSE separated mFRR into a standard product, mFRRd, in line with the MARI model, and a non-standard mFRRn that does not go to the European platform. In the same drafts the standard product was to have a 2.5-minute preparation period, a 10-minute linear ramp and a 10-minute deactivation. Always check the final parameters in PSE's current documents.
- 2 December 2026: isolated mode, limit of 0 MW
- 3 to 9 December 2026: on working days between 09:00 and 13:00 the limit is ±50 MW, and isolated mode applies at other times
- from 9 December 2026: ±100 MW
- from 19 January 2027: ±300 MW
- from 2 June 2027: ±600 MW
Why control, not the battery, decides the result
Two storage systems with identical batteries can perform very differently if one runs a simple charge-low, discharge-high schedule and the other can reconcile several tasks at once. With MARI, that gap can widen, because one more task is added to the existing ones: readiness to be activated on the operator's instruction, with a defined reaction time and ramp profile.
Typical conflicts an EMS has to resolve automatically:
If a person resolves these conflicts from a spreadsheet, it cannot be sustained at market cycles of a few minutes. The rules have to live in the system.
- the arbitrage plan wants to charge in a given window, while an upward-regulation bid needs energy available to discharge
- PV surplus wants to go into the battery, while a downward activation needs free headroom
- the battery, EV chargers and the facility share one grid connection with limited power
- the battery manufacturer derates power at high temperature or on a BMS alarm
How to rank priorities: system service, arbitrage, self-consumption
The simplest way to bring order to the logic is layers. The top layer holds hard constraints that must never be violated. Below it come commitments, and last comes optimisation.
The order of layers 2 and 3 is not dogma. At a site with a large PV installation and expensive peak consumption, self-consumption can be worth more than a system service. What matters is that this choice is an explicit parameter, not a side effect of code. It also helps if every control decision is logged together with its reason, because that lets you answer why the battery did what it did when reviewing settlements and performance. Reporting tools such as Go2EV Analytics serve that purpose.
One more practical point: an energy reserve matters as much as a power reserve. A bid for a given power over a given time means the state of charge must stay within a window that allows delivery. That window has to be calculated dynamically, not set once and left.
- Layer 1, hard constraints: safety and BMS limits, connection capacity, the permitted state-of-charge range. Nothing overrides these.
- Layer 2, commitments: bids and activations of system services, including mFRR. They require energy and power to be reserved for the period the bid covers.
- Layer 3, optimisation: price arbitrage and PV self-consumption. They use whatever is left after the layers above.
A single source of truth about the storage state
A common weakness of older installations is several inconsistent values for the same quantity: state of charge from the BMS, a different one from the inverter, a third in the supervisory system. When control relies on conflicting numbers, the reserve calculated for a market bid is uncertain.
It is worth defining one authoritative representation of state in the EMS, covering:
The connection limit also applies to EV chargers if they sit on the same connection. We describe how to share limited power in our article on grid flexibility and EV charging. For storage the principle is the same: what you can offer to the market is what remains after the site's own needs.
- state of charge and the range that may be used
- available charge and discharge power, reduced for temperature limits and alarms
- the grid connection limit and the current load of other consumers
- timestamps and measurement quality, so the system knows when data is stale
Integrating equipment from different manufacturers
The battery, PV inverter, meter, chargers and supervisory system rarely come from a single supplier. If the control logic is embedded in one manufacturer's software, changing the rules makes you dependent on their release schedule and pricing. The alternative is an integration layer that translates each device's protocols and interfaces into a common model, with the control logic working on that model.
The benefits are concrete:
We build this kind of setup as part of Go2EV integrations, connecting storage, PV, chargers and grid connections in one system. The details naturally depend on which interfaces the specific devices expose.
- replacing or adding a device does not require rewriting the rules
- the same rules can serve several sites with different hardware
- the logic can be tested against simulated devices
Market rules will change: configuration or a separate project
PSE's own schedule shows that conditions shift every few weeks and months: exchange limits grow in steps until June 2027 and the transition period runs to December 2027. On top of that come changes to grid codes, products and tariffs. So the question is not whether the rules will change, but how expensive each change will be.
In practice changes fall into two categories. Changes that should be configuration:
Changes that genuinely need a project are a new type of service or a new communication channel with the market. It helps when configuration is versioned, testable against historical data and reversible. For a broader view of trading energy from storage, see our article on battery storage and energy trading.
- priority order and price thresholds
- time windows, power limits and energy reserves
- ramp and preparation-time parameters
- operating schedules for individual sites
How to start: a checklist
If you own a battery or plan one, start by reviewing what already works. You do not need to replace the system straight away.
- List the data sources for state of charge, power and consumption and check whether they agree.
- Define and write down the hierarchy: what is a hard constraint, what is a commitment and what is optimisation.
- Check with your distribution system operator and with the party through which you access the market what requirements your installation must meet. PSE joining MARI does not automatically admit every unit.
- Find out which control parameters can be changed today without a developer, and which cannot.
- Inventory your devices and their interfaces to assess dependence on a single manufacturer.
- Run your scenarios conservatively, assuming small cross-border volumes in the first months.
- Turn on logging of control decisions and reporting, so you can assess the logic on real data after a few weeks.