    Planning fleet charging under the grid connection limit using vehicle schedules from TMS – lower costs and more vehicles on the same connection.

    Author: Go2EV team · Last updated:

    The problem: the connection runs out before electrification plans do

    Bus depots, logistics centres and fleet bases quickly hit their grid connection limit. Every DC charger adds tens or hundreds of kilowatts, and upgrading the connection takes approvals, time and significant investment.

    The naive approach – charging every vehicle at full power on arrival – creates short but high demand peaks. These peaks drive both required capacity and charges.

    The solution: planned, not random, charging

    Most fleet vehicles stay at the depot longer than they need to charge. If the system knows when a vehicle leaves and how much energy it needs, it can spread charging over time and keep total demand under the limit.

    • arrival and planned departure times from TMS
    • battery state of charge from telematics or the charger
    • energy needed for the next route
    • current demand of other loads on site
    • grid connection limit and contracted power

    How it works in practice

    An optimisation engine recalculates the charging plan every few minutes and sends power limits to chargers via OCPP. Vehicles leaving earlier get priority, and when other loads increase, charging is automatically reduced.

    Dispatchers see the plan and can raise a vehicle's priority manually. The system also flags the risk that a vehicle won't be ready on time – in advance, not after the fact.

    Business results for the site

    • more vehicles served on the existing connection
    • a costly connection upgrade postponed or reduced
    • lower capacity charges thanks to flatter peaks
    • charging during cheaper energy hours
    • confidence that vehicles are ready on departure

    Where to start

    The first step is data analysis: the site's load profile, fleet schedules and charger parameters. This shows how many vehicles realistically fit on the current connection and what optimisation will deliver. Go2EV Depot runs this process as part of its pilot programme.